2.2.0.260 - misleading or bogus "ended" Job Duration Alert
PDinCA
Posts: 642 Silver 1
Job runs hourly and has a typical duration of under 20 seconds. Having just rewritten the underlying SP and added additional data points to evaluate, the job now runs between 1:35 and 2:26. The latest exec ran in 2 minutes 31, which gave rise to a "Job duration unusual" alert based on the prior 10 execs. No problem so far. "Time raised: 15 Apr 2011 7:27 PM (UTC-04)"
When an hour later an Alert arrived informing me that the Alert "Time ended" was 15 Apr 2011 8:27 PM (UTC-04), i.e., a full hour later for a job lasting 2m31secs, it looks confusing.
Is this the intended way the "Ended" Alert should work? My actual Alert shows:
I've also had an instance where I received an "Ended" Alert for a job that purported to run for a solid week! It didn't. It just happened to run for an unusual duration and then 7 days later ran again, according to it's normal schedule.
I feel misled into investigating something that isn't an issue in reality.
Would you clarify, please, or is this a bug?
Thanks.
When an hour later an Alert arrived informing me that the Alert "Time ended" was 15 Apr 2011 8:27 PM (UTC-04), i.e., a full hour later for a job lasting 2m31secs, it looks confusing.
Is this the intended way the "Ended" Alert should work? My actual Alert shows:
Job name: _HourlyMeterSampling User: sa Job started at: 15 Apr 2011 7:25 PM Job ended at: 15 Apr 2011 7:27 PM Job outcome: Succeeded Duration: 00:02:31 Baseline duration (median of last 10 runs): 00:01:40 Deviation from baseline: 50% Job next scheduled to run at: 15 Apr 2011 9:25 PMAs you can see, the Job started and ended times are correct, along with the duration. As the "Job next scheduled to run at:" value is TWO HOURS after the alerted Job, there appears to be a problem with the Alert in that the 8:25 PM execution is detected as the "Ended" trigger for the original Alert.
I've also had an instance where I received an "Ended" Alert for a job that purported to run for a solid week! It didn't. It just happened to run for an unusual duration and then 7 days later ran again, according to it's normal schedule.
I feel misled into investigating something that isn't an issue in reality.
Would you clarify, please, or is this a bug?
Thanks.
Jesus Christ: Lunatic, liar or Lord?
Decide wisely...
Decide wisely...
Comments
This is not a bug but it is designed behaviour.
SQL Monitor has two types of alerts Event alert and Continuous alert. "Job duration unusual" alert is classified as continuous alert.
The designed behaviour is that, if say the current job run deviates from base line (as per configuration). This will then create a "Job duration unusal" alert. Now this alert will remain active till the subsequent job run deviation is within the threshold (as per configuration).
In other words, the alert will remain active till it has verified that the subsequent job runs are not deviating as per the baseline.
Hope this explains.
Thanks,
Priya
Project Manager
Red Gate Software
What happens when the job runs for the 2nd time and the alert is "active", do I get another Job Duration Unusual Alert? That's all I'd want to see - that each incident is reported to me. I can look at the occurrence history to determine if I have an ongoing issue...
If there is a way to change the Alert, perhaps in a future version, so that the User can choose between a "Continuous Alert" and "Event Alert", I for one would be less confused but still able to look into a potential issue given a succession of the same Job Duration Unusual alerts. Your thoughts?
Decide wisely...
If the job runs for 2nd time and the alert is still "active" then the "Job duration unsual" alert will remain active. Now, suppose there is a 3rd run and this time the deviation is within the range (no longer above configuration threshold) then the "Job duration unusual" alert will be marked as "ended". Now say there is 4th run and the job deviates again. Then you will get a new "Job duration unusual" alert.
In other words, the alert will remain active till it has verified that the problem no longer exists. If the problem comes back again then a new instance of this alert will be created.
Thanks for your feedback on this. We will definitely consider and review the behaviour of this alert.
Regards,
Priya
Project Manager
Red Gate Software
I hope this kind of scenario, not uncommon I would venture, can be used as collateral when considering providing the option to alter this to an Event Alert.
1 vote hereby cast for this enhancement.
Thanks.
Decide wisely...
Regards,
Priya